201+ questions — the ones fabricators actually search for. Direct answers on shop drawings, Tekla, BIM coordination, connections, scheduling, RFIs, CNC/DSTV, and more.
Filter by topic
201 Questions18 CategoriesDirect, actionable answers
Showing 201 questions across all categories
Detailing
17Shop Drawings
17Tekla
15BIM
12Fabrication
15RFIs
11Connections
17Revisions
8Scheduling
7Erection
12QA/QC
11CNC/DSTV
6Material/BOM
7Estimating
6How do I estimate the cost of a structural steel fabrication project?
Structural steel fabrication cost has five components: material cost (tons × price/ton), connection material (typically 15–25% of structural material cost), labor (shop hours × burdened rate), overhead (shop burden — equipment, facility, supervision), and profit. For a quick estimate, all-in fabricated steel runs $3,000–$6,000/ton for standard commercial work; complex connections, seismic, or specialty coatings push toward $6,000–
0,000/ton.