Inside Tectonix’s 100% Internal QA/QC Workflow for Structural Steel Detailing

See inside Tectonix’s 100% internal QA/QC workflow for structural steel detailing. Learn how structured checks, Tekla models, and revision control protect your shop.

Inside Tectonix’s 100% Internal QA/QC Workflow for Structural Steel Detailing

AI ANSWER SUMMARY

Tectonix’s 100% internal QA/QC workflow for structural steel detailing is a structured, in-house review system that runs from model build through issued-for-fabrication drawings. Using Tekla Structures, every piece and assembly is checked by multiple team members, passed through standardized checklists, and tracked in a formal revision register. Fabrication-impacting changes are flagged, erection sequences are reviewed, and no drawing is intended to reach the shop floor without a clear, current revision status.


Introduction: Why QA/QC in Detailing Decides Your Project Risk

Most structural steel fabricators don’t lose time because steel can’t be cut, drilled, or shipped. Time is lost when a drawing is wrong, a model is incomplete, or a revision never makes it to the shop floor.

When QA/QC in detailing is weak, the result shows up as RFIs, rework, patch plates, out-of-sequence erection, and frustrated field crews. For fabricators working across commercial, industrial, and institutional projects, the question is not just "Are the drawings accurate?"—it’s "Can we trust every revision that reaches the shop and the field?"

Inside Tectonix’s 100% internal QA/QC workflow for structural steel detailing, the focus is on controlling that risk. The process is built around Tekla Structures 3D modeling, fabrication-focused detailing, and disciplined revision control so fabricators can protect throughput and keep erection on schedule.


How Tectonix Builds QA/QC Into Every Stage of Structural Steel Detailing

A reliable QA/QC workflow doesn’t happen at the end of a project—it is built into every stage from intake through closeout. Tectonix uses a structured, repeatable sequence that fabricators can see and measure.

1. Project Intake and Standards Alignment

Before a single member is modeled, Tectonix aligns the QA/QC approach with the fabricator’s real-world constraints:

  • Gather fabricator standards: shop preferences, connection libraries, camber rules, bolt preferences, surface prep, and paint/galvanizing requirements.
  • Review contract documents: design drawings, specs, addenda, and BIM coordination requirements.
  • Clarify deliverables: what is required for approvals, shop, erection, CNC, and any BIM export formats.
  • Risk identification: highlight ambiguous connections, atypical loading, complex geometry, and potential field-fit issues.

This front-end work sets the QA/QC criteria that every drawing and model element must meet.

2. Tekla Model Creation With Built-In Controls

With Tekla Structures as their primary platform, Tectonix embeds controls at the model level:

  • Standardized templates and attributes so piece marks, sequences, and phases line up with shop workflows.
  • Connection detailing based on engineer requirements and fabricator standards, with clear differentiation between typical and non-typical connections.
  • Clash awareness during modeling, setting up later BIM coordination and clash-checking.
  • Preliminary erection logic considered as members are placed—field access, crane reach, splice locations, and stability.

By the time drawings are generated from the model, most basic dimensional, fit-up, and connectivity errors are already trapped.

3. Internal Multi-Layer Drawing Checks

Every drawing set passes through multiple internal checkpoints before it ever reaches a fabricator:

  • Detailer self-check: The original detailer runs through a defined checklist covering dimensions, weld symbols, bolt info, material grades, camber, and field bolt access.
  • Secondary detailer review: A second detailer reviews the drawings and associated Tekla views for constructability, connection logic, and clarity for the shop.
  • Dedicated checker review: A checker with a broader project view looks for alignment with design intent, sequences, and shop/field workflows—ensuring no local optimization compromises the bigger picture.
  • Project manager sign-off: The U.S.-based project manager confirms scope alignment, submittal completeness, and that all known RFI items and design changes are reflected and documented.

Only after these steps are complete are drawings submitted for approval or fabrication, depending on contract requirements.


Inside the 100% Internal QA/QC Workflow: Step-by-Step

The phrase "100% internal QA/QC" is only useful if it is practical and traceable. At Tectonix, that workflow typically follows a repeatable path.

Step 1: Scope Capture and RFI Structuring

  • Review all design documents and addenda against bid scope.
  • Log open questions as structured RFIs with drawing references, location, and proposed resolutions.
  • Flag schedule-impacting issues early so fabricators can plan sequencing workaround if needed.

Step 2: Model QA Checks

Before bulk drawing production begins, the model is checked for:

  • Member sizes and grades against design drawings and schedules.
  • Connectivity of primary and secondary members (no floating steel).
  • Elevations and datum consistency across grids and levels.
  • Anchor bolt locations relative to grid and foundation plans.

Issues found here are resolved in the model so they don’t proliferate across hundreds of drawings.

Step 3: Shop Drawing Generation and First-Pass Review

  • Generate piece and assembly drawings from the Tekla model.
  • Run a first-pass drawing audit: dimensions, hole patterns, bolt types and quantities, welds, camber, coatings.
  • Confirm that piece marks align with shop tracking systems and sequences.

Step 4: Formal QA/QC Checklist and Markup Cycle

Tectonix uses standardized checklists tailored to structural and miscellaneous scopes. Typical checks include:

  • Dimensional accuracy: Major framing dimensions, critical clearances, and tolerance-sensitive interfaces.
  • Connection details: Plate sizes, weld sizes, bolt edge distances, slip-critical vs. bearing, field vs. shop welds.
  • Fabrication readiness: Are all features shown clearly for burning, drilling, coping, and assembly?
  • Erection clarity: Clear piece identification, field bolts, erection notes, and sequences as applicable.

Markups are handled within Tekla and/or PDF environments, then resolved and rechecked before sign-off.

Step 5: Internal QA Sign-Off and Revision Register Update

Once drawings pass all internal checks:

  • The project manager confirms completeness against the current scope and design status.
  • All drawings are logged in a revision register, including:
    • Drawing number and title
    • Revision number and date
    • Description of changes
    • Who made the change and who checked it
  • Fabrication-impacting changes are tagged so fabricators can focus their attention where it affects the shop and field.

Step 6: Controlled Issuance and Feedback Loop

Drawings are then:

  • Issued with clear status: For Approval, For Construction, or For Fabrication.
  • Accompanied by transmittals tied back to the revision register.
  • Tracked against responses from engineers, GCs, and fabricators.

Any returned comments or change directives trigger a controlled cycle: update model → regenerate affected drawings → re-run QA/QC → update revision register → reissue.


How Revision Control Protects Your Shop and Field Crews

For fabricators, the biggest risk is often not that the initial drawing is wrong, but that the right revision never reaches the right place.

Tectonix’s revision control is built to protect against that.

Complete Revision Register on Every Project

Every project maintains a live revision register that tracks:

  • What changed: connection details, member sizes, camber, hole patterns, splice locations, or notes.
  • Where it changed: specific drawings and model elements.
  • When it changed: dates and sequence of revisions.
  • Which version is current: clearly flagged so superseded drawings are easy to identify.

This allows fabricators to match what is in their document control system with what is actually current in the model.

Fabrication-Impacting Changes Flagged Separately

Not every revision requires the same level of shop disruption. Tectonix:

  • Tags fabrication-impacting changes (e.g., hole relocations, plate thickness changes, new stiffeners) separately in the register.
  • Calls out field-impacting changes that may alter lift plans, access, or temporary bracing.

This allows fabricators to prioritize internal communication and minimize wasted time on low-impact tweaks.

Clear Status So Superseded Drawings Don’t Reach the Floor

The workflow is designed so that:

  • No drawing is intended to reach the shop floor without clear revision status.
  • No CNC file is intended to be run from a superseded revision.

When combined with the fabricator’s internal document control, this significantly reduces the risk of cutting or assembling from outdated information.


What Structural Steel Fabricators Should Look for in a QA/QC Partner

Whether working with Tectonix or another detailing team, fabricators can evaluate QA/QC based on practical criteria, not just promises.

1. Named, Accountable Project Management

Every Tectonix project is led by a named U.S.-based project manager who:

  • Issues daily morning progress reports
  • Serves as the single point of accountability
  • Coordinates responses with engineers, GCs, and other trades

Fabricators should expect that same clarity from any detailing partner.

2. Documented Internal Checklists and Standards

Ask for:

  • Sample QA/QC checklists used on structural and miscellaneous steel.
  • Examples of marked-up drawings with checker comments and resolutions.
  • Explanation of how shop standards are embedded into templates and models.

3. Tekla and BIM Coordination Capability

For complex projects—healthcare, data centers, industrial plants—detailing QA/QC must extend into BIM coordination:

  • Tekla-based models that integrate into the project’s BIM environment.
  • Clash-checking against concrete, MEP, and architectural models.
  • Ability to export and coordinate with the GC’s or owner’s BIM standards.

4. Revision Control That Matches Your Internal Systems

Detailers and fabricators need compatible systems for:

  • Naming conventions
  • Revision sequencing
  • Transmittal tracking
  • CNC file versioning

A strong partner will work with you to align standards instead of forcing a one-way process.


How Tectonix’s QA/QC Reduces RFIs, Rework, and Schedule Hits

The point of a robust QA/QC workflow is not paperwork—it is reducing friction in the shop and field.

Fewer RFIs Through Structured Questions

Instead of scattered emails and calls, Tectonix uses structured RFI documentation that includes:

  • Clear drawing and detail references
  • Concise description of the conflict or missing information
  • Proposed resolution where appropriate
  • Notation of potential schedule impact

This approach speeds responses from engineers and GCs and reduces repeated back-and-forth.

Less Rework in the Shop

Because every drawing is checked internally before it reaches fabrication:

  • Incorrect hole patterns, missing cope details, or mis-located stiffeners are caught earlier.
  • CNC files are less likely to require manual overrides or last-minute adjustments.

Over a full project, that translates into fewer re-cut pieces, less scrap, and more predictable throughput.

More Predictable Erection Sequences

With detailing and QA/QC built around erection logic, field crews see:

  • Clear layouts for anchor bolt patterns and base plates.
  • Rational splice locations and member sequencing.
  • Fewer surprises where steel conflicts with other trades.

That stability is especially valuable on tightly phased commercial, industrial, and institutional work where crane time and access are constrained.


Common Mistakes to Avoid

  • Relying on approval stamps as the only quality check. Engineer or GC approvals are important, but they do not replace a structured internal QA/QC process focused on fabrication and erection.
  • Treating revisions informally through email only. Untracked changes lead directly to superseded drawings reaching the shop; always insist on a controlled revision register and formal issuances.
  • Skipping model-level QA before bulk drawing production. If the Tekla model is wrong, every drawing derived from it will carry the same error across dozens or hundreds of pieces.
  • Ignoring fabricator standards in detailing. When detailing is done in a vacuum, shop workarounds, extra welding, and field fixes become routine instead of rare.
  • Underestimating miscellaneous steel complexity. Stairs, rails, and ladders often create more field problems than main framing when QA/QC is lighter on these scopes.
  • Assuming BIM coordination is “someone else’s job.” If the detailer’s model is not actively coordinated, clashes with concrete, MEP, and architectural elements often show up during erection instead of in the model.

Frequently Asked Questions

How does Tectonix’s 100% internal QA/QC workflow actually reduce RFIs on a project?

RFIs often originate from unclear, incomplete, or conflicting information in the drawings and model. Tectonix’s workflow attacks this at multiple points. During intake, open questions are logged as structured RFIs before modeling begins, reducing late-stage surprises. During modeling and drawing production, checklists force detailers and checkers to resolve common conflict areas—connection types, edge distances, field welds vs. shop welds, and fit-up with concrete and other trades. When questions genuinely require engineer or GC input, they are documented with precise references and proposed resolutions, which speeds turnaround. The result is fewer RFIs overall and faster responses to the ones that matter.

What does “100% internal QA/QC” mean in practical terms for fabricators?

For fabricators, "100% internal QA/QC" means that every drawing and related model element has been reviewed by multiple Tectonix team members before it arrives in your inbox. The detailer, a secondary detailer, a checker, and a U.S.-based project manager each have defined roles in the review sequence. Checks are performed using standardized procedures instead of ad-hoc spot checks. Revisions are controlled through a formal register, and fabrication-impacting changes are flagged. This reduces the chance that you will have to act as the last line of defense, catching basic errors just before cutting or assembly.

How are fabrication-impacting changes flagged and communicated so shops don’t miss them?

When a revision affects something the shop must physically change—such as plate thickness, hole positions, added stiffeners, or a change from slip-critical to bearing bolts—Tectonix flags it explicitly in the revision register and in the drawing revision description. Transmittals identify which drawings have changed and why, so fabricators can quickly focus on affected pieces and assemblies. Many shops pair this with their internal document control and nesting software, but the initial clarity starts with a disciplined register and clear, concise change descriptions from the detailing team.

How do daily morning progress reports tie into QA/QC and schedule control?

Daily morning progress reports from the U.S.-based project manager give fabricators ongoing visibility into both production and QA/QC status. These reports typically cover what was modeled or detailed the previous day, which drawings are in checking, which RFIs are outstanding, and what is planned for the current day. When a QA/QC issue, design change, or coordination conflict arises, it shows up in these reports quickly, allowing fabricators to adjust internal sequencing, prioritize urgent checks, or shift shop focus. This reduces surprise bottlenecks and makes it easier to keep fabrication and erection aligned with the project schedule.

How does Tectonix’s workflow coordinate with engineers, GCs, and other trades during BIM and clash-checking?

On projects requiring BIM coordination, Tectonix uses Tekla Structures to contribute a detailed structural and miscellaneous steel model into the broader coordination environment. QA/QC extends beyond pure steel geometry to include clash-checking against concrete, MEP, and architectural models as directed by the project’s BIM execution plan. When clashes or inconsistencies are found, Tectonix documents them clearly, often with snapshots and suggested resolutions, and coordinates through the project’s designated BIM channels or coordination meetings. This reduces downstream field conflicts and keeps steel erection from becoming the bottleneck when other trades are involved.

What happens when late design changes arrive after detailing is mostly complete?

Late design changes are a reality on many commercial, industrial, and institutional projects. When they occur, Tectonix first logs them in the revision register and evaluates which parts of the model and which drawings are affected. Changes are then implemented in the Tekla model, and all impacted drawings are regenerated or updated. Each updated drawing goes back through the QA/QC workflow—not just a quick patch—because changes in one area can create secondary effects. Only after passing checks are the revised drawings issued with updated revision numbers and clear descriptions of the changes. Fabrication-impacting changes are highlighted so shops can react efficiently.

Can Tectonix ramp QA/QC capacity to match fast-track or phased fabrication schedules?

Yes. Tectonix can ramp detailing and QA/QC capacity up or down to align with phased releases, fast-track schedules, or shifting priorities. Because the QA/QC workflow is standardized, additional internal resources can be added without diluting the quality controls. This is particularly valuable when a project accelerates unexpectedly or when a fabricator wins additional work and needs to expand detailing capacity without immediately increasing internal headcount.


Conclusion: Turning Detailing QA/QC Into a Competitive Advantage

For structural steel fabricators, detailing quality is not just a technical issue—it is a throughput, schedule, and risk issue. Inside Tectonix’s 100% internal QA/QC workflow for structural steel detailing, every step is aimed at giving fabricators reliable, fabrication-focused drawings and models backed by disciplined revision control.

By combining Tekla Structures modeling, multi-layer internal checks, structured RFIs, and a complete revision register, Tectonix helps reduce RFIs, rework, and schedule disruptions on complex commercial, industrial, and institutional projects.

Send us your next project for a 24–48 hour scope review and see how a dedicated QA/QC workflow can support your shop standards, protect your schedule, and keep erection moving in the field.

Send us your next project for a 24–48 hour scope review and see how a 100% internal QA/QC workflow changes your detailing reliability and shop throughput.